Our community has grown significantly since we first began meeting the needs of area families more than 60 years ago. For the Sanford-Springvale Y to fulfill its mission of improving the quality of life of those who live and work in our community, we also need to expand and grow. To that end, we are excitedly undergoing phase one of an expansion project that will enable us to not only create opportunity for growth today but fulfills the expectations of our community tomorrow.
Through the generosity of our community donors, we have raised enough funds to get phase one underway! The site work is now complete and a weather-tight shell is currently being constructed, as we actively work to raise the additional $2 million needed to complete this phase.
We hope that you will partner with us in making your community a better place to live by making a tax-deductable gift to our Expansion Project. Download a pledge form today and return it to Andy Orazio.
Expansion Details:
- Two story expansion is 22,000 square feet
- Local vendors will be used for 90 percent of project
- Construction Manager is Ron Woodward; Petrona Inc
- Lead Architect is David Joy, Joy and Hamilton, Inc.
- Site work contractor is Richard Levesque, Levesque Excavation, Inc.
- Phase one expansion cost is $3.2 Million (The Y has raised $1.3 million dollars and additional in-kind material donations)
- We will focus on building a weather tight space before winter and will raise the remainder of funds needed through other donations and/or in-kind opportunities.
- No finishing date has been set. Completion of Phase One will depend on raising the needed funds
Construction Update
Check out weekly updates of how the construction process is coming along
July 14: YMCA and the community break ground
July 16: Site work begins: logging begins on future site of expansion
July 26: Site work continues: Logging complete and excavation begins
August 5: Excavation continues and sewer works begins
August 13: Site work continues and foundation work begins
August 18: Site work continues and foundation form prep work complete
August 26: Site work continues and foundation is poured
September 8: Site work and foundation, sewer work continues
September 13: Site work and foundation work continue
September 27: Site work and foundation work continue
November 20: Site work and foundation work continue